Over 30 years of reporting on Congress, federal agencies and the White House for corporate America as well as national trade and professional associations.

Appeals Court Decision May Trump House Pipeline Bill

Pipeline & Gas Journal - September 2017 for the original article go HERE.

The House passed two pipeline bills – which could run into trouble in the Senate for lack of Democratic support – amid continuing industry unhappiness with federal and state regulatory agency foot-dragging on permit approvals.

The U.S. Court of Appeals for the District of Columbia Circuit, which has authority to clarify federal regulations, made decisions on two separate pipeline cases in June. In one of them, the court clarified that the Federal Energy Regulatory Commission (FERC) has the right to grant a pipeline an exemption from state law in the event a state drags its feet on permitting new construction.

The court’s actions – and one of the House bills – are particularly germane with regard to Transco’s 200-mile Atlantic Sunrise pipeline, meant to deliver Pennsylvania shale gas south. FERC approved the project in February. However, the state of Pennsylvania has yet to grant the three permits necessary for the $3 billion project to break ground.

However, the D.C. court, while clarifying FERC’s exemption authority, a victory for the pipeline industry, also made it clear that deadlines for issuance of  permits under the Clean Water Act (12 months) and Clean Air Acts (18 months) take precedence over timeframes FERC typically establishes under its Natural Gas Act authority. FERC normally gives state and federal agencies 90 days to issue permits after it approves an environmental impact statement.

“We are still working with the Pennsylvania Department of Environmental Protection and are awaiting clearances from the state before we can begin pipeline construction in Pennsylvania,” said Transco spokesman Chris Stockton. The project includes 183 miles of greenfield pipeline to gas from Pennsylvania and move it south to Maryland, Virginia, North Caroline and South Carolina.

“After nearly three years of intense regulatory scrutiny, it is time for our own state government to complete its review of this important infrastructure project so that Pennsylvanians can immediately benefit from the economic growth and jobs it promises to deliver,” said Rep. Mike Turzai, speaker of the Pennsylvania House of Representatives, in a June statement.

The failure of states to participate in a timely manner in the FERC completion of an environmental impact statement and their ability to withhold permits after FERC project approval were the rationales for the Promoting Interagency Coordination for Review of Natural Gas Pipelines Act (H.R. 2910) passed by the House on July 19 on a mostly party-line vote. The legislation requires that federal and state agencies conduct their respective permit reviews concurrently with FERC as it develops its environmental impact statement.

The second bill that passed the House was the Promoting Cross-Border Energy Infrastructure Act (H.R. 2883). It replaces the presidential permitting approval needed before constructing an oil and gas pipeline or electric transmission line that crosses a border with Canada or Mexico with a more transparent, efficient and effective review process.

Because H.R. 2910, strongly supported by the Interstate Natural Gas Association of America (INGAA), may get hung up in the Senate, the bigger impact on pipeline construction approvals may come from the two cases decided by the D.C. appeals court. One case involved Millennium Pipeline Company, LLC which asked the court to force New York state to certify Millennium’s request for a water quality certification, required under Section 401 of the Clean Water Act, that would allow Millennium to construct its Valley Lateral Project. Millennium submitted its application with the state agency in November 2015, but almost 19 months later, the agency has still failed to act on Millennium’s application.

In the other case, Tennessee Gas Pipeline Co., LLC, a subsidiary of Kinder Morgan, argued that a local government was refusing to issue a permit under the Clean Air Act for additional compressor capacity.

FERC approved Millennium’s 7.8-mile Valley Lateral in November 2016 after completing an environmental impact statement earlier that year. Millennium applied for a water quality certificate from the New York Department of Environmental Conservation in November 2015. The NYDEC did not participate in that FERC EIC because it argued Millennium had not submitted a completed permit application until August 2016.

Under the Clean Water Act, New York had 12 months to complete its review of the Millennium application. The state argued the clock began in August 2016 when it judged Millennium to have submitted a complete application. The D.C. Court essentially disagreed and said Millennium could file a request for an exemption from the CWA with FERC, and FERC could grant it. FERC has never granted an exemption like that for a pipeline, though it has done so for hydro projects.

The Pennsylvania Department of  Environmental Protection has held up a permit to Transco for Atlantic Sunrise because of nitrogen oxide emissions generated by construction equipment involved in building the pipeline. Those emissions would violate the Clean Air Act. However, Transco has asked the agency to allow it to claim emission-reduction credits earned when improving air pollution from one of its compression stations on the existing Transco pipeline in Ellicott City, MD. That “offset” would presumably allow Pennsylvania to approval the permit.

But clean air issues aren’t the only state regulatory barriers in Pennsylvania. The state has sent Transco technical deficiency letters having to do with applications for two other permits, one dealing with water obstruction and encroachment, the other with erosion and sediment control.

Author bio: 
Mr. Barlas, a freelance writer based in Washington, D.C., covers topics inside the Beltway.